Forum home » Delegate support and help forum » Microsoft Project Training and help » MS Project

MS Project

resolvedResolved · High Priority · Version 2007

MS Project

How do you link different project plans.

RE: MS Project

Hi Thomas

Thanks for your question. Create a blank project and then from the insert menu choose Insert project. Once they are both in your plan you can drag and link between the tasks you'd like tc connect. If necessary double click on the link created and change it for a more suitable link. Close and save your files. You can delete the temporary project, the remaining files are now linked.
I hope this helps.
Kind regards,
Andrew

Mon 8 Dec 2008: Automatically marked as resolved.


 

MS Project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.