Configuration of formats

resolvedResolved · Low Priority · Version 2007

Gordon has attended:
Project Intro Intermediate course

Configuration of formats

Any way of configuring Project2007, to allow other types of resource.

Or having differnt sorts of units apart form time, cost,....is it possible to confirgure tohave 'Kilograms' for instance?

RE: Configuration of formats

Hi Gordon

Thanks for your question. The resource types are fixed as are the time and cost variables used for scheduling however if you want to track material resources you can specify a material label (e.g. Kg, m3, per unit of material used) to suit your requirements.

I hope this helps - let us know if you need any further information.

Kind regards,
Andrew

Fri 12 Dec 2008: Automatically marked as resolved.


 

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips


Server loaded in 0.07 secs.