Lag
Resolved · Urgent Priority · Version 2003
Emma has attended:
Project Intro Intermediate course
Lag
Ho w do I enter lag? I keep forgetting where it is!!!
RE: Lag
Hi Emma
Thanks for your question. There are two places this can be added. You can either double click on the arrow that links to the task you want to delay or double click on the successor and go to the predecessors box. In either case you will find a cell labeled lag which you can use to enter the delay you require.
I hope this helps - let us know if you have any further questions.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Show or hide toolbar ScreenTipsOn the Tools menu, go to Customize, and then select Toolbars. |