microsoft project training - Milestone

resolvedResolved · Low Priority · Version Standard

Hereward has attended:
Project Intermediate course
Project Advanced course

Milestone

How do I create milestone?

RE: milestone

Hereward

Set the duration at the side of your task as zero days


 

MS Project tip:

Use Autofill in MS Project

a. Complete 1st entry
b. Select cell with entry to be copied
c. Click & drag autofill handle over the lines to also contain the same information. (the autofill handle is the little black square in the bottom right hand corner of the heavy lack outline on the selected cell)