Forum home » Delegate support and help forum » Microsoft Project Training and help » Project

Project

resolvedResolved · Medium Priority · Version 2003

Mark has attended:
Excel Introduction course

Project

how can i make red(critical) bars not critical,i done 3 phases the same and project made the last one red(critical)
mark

RE: project

Hi Mark

Project calculates the critical tasks in your project as those that influence the end date of your plan and have no slack or float (that is a change in critical tasks will directly change your end date)

If you'd rather not see the critical path you can work in the Gantt View. By default the critical path is displayed in the Tracking Gantt view.

I hope this helps - let us know if you have any further questions.


Kind regards,
Andrew

Fri 12 Dec 2008: Automatically marked as resolved.


 

MS Project tip:

Compare Work and Duration

Duration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field.

View all MS Project hints and tips


Server loaded in 0.09 secs.