Project
Resolved · Medium Priority · Version 2003
Mark has attended:
Excel Introduction course
Project
how can i make red(critical) bars not critical,i done 3 phases the same and project made the last one red(critical)
mark
RE: project
Hi Mark
Project calculates the critical tasks in your project as those that influence the end date of your plan and have no slack or float (that is a change in critical tasks will directly change your end date)
If you'd rather not see the critical path you can work in the Gantt View. By default the critical path is displayed in the Tracking Gantt view.
I hope this helps - let us know if you have any further questions.
Kind regards,
Andrew
Fri 12 Dec 2008: Automatically marked as resolved.
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Compare Work and DurationDuration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field. |