Budgets
Resolved · Low Priority · Version 2003
Roger has attended:
Project Introduction course
Budgets
How to relate internal and external billing and gross margin to timelines
RE: Budgets
Hi Roger
Thanks for your question. Two things might help to track this. On the resource sheet (View > Resource sheet) you will see that each resource has a code value (the last column in the table). You could use this to enter management or cost centre codes to align a resource with a particular budget heading. In addition back on the Gantt view you could add in a cost column (right click on a column heading e.g. Task Name and choose insert column and select the fixed cost field)
You can record non resource related costs for each task so that expenditure is counted whether or not you have costed resources assigned to the task.
I hope this helps - let us know if you have any further questions.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Change default view – Project 2010a. In Project, click on the File tab |