baselines

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » Baselines

Baselines

resolvedResolved · Low Priority · Version 2003

Celina has attended:
Project Introduction course

Baselines

How do you view multiple baselines?

RE: Baselines

Hi Celina

you can view multiple baselines in Project by going from the following menu:

View > More Views > Multiple Baselines Gantt

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew


 

MS Project tip:

Email a Task

When you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system.

1.In a task sheet, select the task or tasks which you want to send a project note.

2.On the File menu, point to Send To, and then select Mail Recipient (as Schedule Note).

3.Under Address message to, select the recipients of your note.

View all MS Project hints and tips


Server loaded in 0.07 secs.