how do i link my task bars

RE: project

Hi Mark

Thanks for your question. A quick way to link your tasks would be to move your mouse pointer over the bar for the task (so you can see the four headed arrow) left click and drag down the screen until you reach the successor task and let go. MS Project drops in a Finish to Start relationship

Hope this helps - let us know if you have any further questions.

Kind regards,
Andrew


 

MS Project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.