Forum home » Delegate support and help forum » Microsoft Project Training and help » How to split resourcs calender

How to split resourcs calender

resolvedResolved · Low Priority · Version 2003

gary has attended:
Project Introduction course

How to split resourcs calender

can you email me answres

RE: how to split resourcs calender

Hi Gary

Thanks for posting to the forum. We're happy to help - can you let me know a little more about the kind of split you are looking to create?

Kind regards,

Andrew

RE: how to split resourcs calender

Hi Gary,

As this question has been left unanswered for a couple of months, the system will automatically mark this query as resolved in the next 5 days if we don't hear from you.

If you still require assistance with this query, please post a reply and we will assist you further.

Thank you.

Rich

Mon 24 Nov 2008: Automatically marked as resolved.


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.