how do you set more than 1 baseline then view them simultaneously?

RE: baselines

Hi Stewart

You can save more than one baseline by going to tools > tracking > save baseline and from the top baseline drop-down choosing the baseline field to store your current plan.

You can see more than one baseline by going to the view menu and choosing more views then selecting multiple baselines Gantt (which shows up to 4)

I hope this is helpful - let us know if you have any further questions.

Kind regards,

Andrew


 