how do you set more than 1 baseline then view them simultaneously?
RE: baselines
Hi Stewart
You can save more than one baseline by going to tools > tracking > save baseline and from the top baseline drop-down choosing the baseline field to store your current plan.
You can see more than one baseline by going to the view menu and choosing more views then selecting multiple baselines Gantt (which shows up to 4)
I hope this is helpful - let us know if you have any further questions.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Project Communityin the help menu type "Tips" then select "Ask the Project community" this takes you into microsofts site where you can ask questions to lots of knowledgeable people.They make up an online group of experienced Project users who answer questions and provide solutions and tips. |