MS Project

Can i create my own custom view.?

RE: MS Project

Hi Paul

thanks for your question - you can create views quite easily in Project. Try this: Go to the View menu and choose More views and click on New. Chose between a single view or one with a split then select the elements you would like to appear in the view.

I hope this helps - let us know if you have any other questions.

Kind regards,
Andrew


 

MS Project tip:

Set default task type - Project 2010

a. In Project, click on the File tab
b. Select Options from left hand side
c. Click on Schedule to set the scheduling options
d. Set the Default Task type box to your chosen option
i. Generally if you plan/estimate your projects using durations you should use fixed duration, and untick the box New tasks are effort driven, if you plan/estimate with person hours use fixed work, or for plans estimated with the proportion of resources time use fixed units, and untick the box New tasks are effort driven)
e. Click OK to apply your changes