Task setup
Resolved · Low Priority · Version 2003
Alpa has attended:
Project Intro Intermediate course
Task setup
How can you start a successor task only after a predecessor task is 75% complete?
RE: Task setup
Hi Alpa
Thanks for your question. You can double click on your successor task and give it's relationship to the predecessor a minus 75% lag. Project will calculate negative lag (lead time) of 75% of the duration of the predecessor and position your successor task accordingly.
I hope this helps. Let us know if you have more questions.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Compare Work and DurationDuration is the timescale within which a task is done; Work is the specific time element used. For example, 3 days work in a duration of 2 weeks. To compare, add the Work field into the Entry table by right clicking a column heading to Add Field. |