How do i enter actual completion?

RE: Project

Hi Paul

thanks for your question. One way you could enter actual completion is to select your task then from the Tools menu choose Tracking > update task

In the dialog that appears record how much has been done (actual) and any remaining duration and click OK. You'll also see the dialog box can accept actual start and finish dates if you prefer.

I hope this is helpful - let us know if you have any other questions.

Kind regards

Andrew


 

MS Project tip:

Use Autofill in MS Project

a. Complete 1st entry
b. Select cell with entry to be copied
c. Click & drag autofill handle over the lines to also contain the same information. (the autofill handle is the little black square in the bottom right hand corner of the heavy lack outline on the selected cell)

View all MS Project hints and tips


Server loaded in 0.08 secs.