Resolved · Low Priority · Version 2003
RE: Project
Hi Paul
thanks for your question. One way you could enter actual completion is to select your task then from the Tools menu choose Tracking > update task
In the dialog that appears record how much has been done (actual) and any remaining duration and click OK. You'll also see the dialog box can accept actual start and finish dates if you prefer.
I hope this is helpful - let us know if you have any other questions.
Kind regards
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Use Autofill in MS Projecta. Complete 1st entry |