Gant Chart
Resolved · Medium Priority · Version 2003
Rahat has attended:
Project Intro Intermediate course
Gant Chart
How do you connect different project project plans together.
RE: Gant Chart
Hi Rahat
Thanks for your question. One way of joining two plans together is to first create a third temporary plan. From this new document use Insert > Project to add in both your plans. Drag to link tasks across both projects (change links from FS by double clicking them and choosing the link type you need). Close and save your files. You can discard the temporary document. The remaining project files have now been linked. Changes in one will impact on the other.
I hope this helps - let us know if you have any other questions.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Format individual bars on your GANTT chartTo draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications. |