Project 2007 - Changing Resource Pools
Resolved · High Priority · Version 2007
David has attended:
Project Intro Intermediate course
Project 2007 - Changing Resource Pools
Hello
I've put together a Revised Resource Pool10 and would like to reassign to my existing Projects.
The Resource sharing Links show the connection to previous Resource Pool2, even after I try to disconnect the Link.
In desperation I've completely deleted my previous Resource Pool2 - trying to connect to my new Resource Pool10.
Unfortunitely the Share Resources options still list the deleted files, with no Reference or Option to link to my new Resource Pool10.
Ultimately, I wish to print out reports from my Master File, giving the Total Resource Hrs covering all Projects.
In a quandery - What do I do from here ????
Look forward to hearing from you soon
Regards
David
RE: Project 2007 - Changing Resource Pools
Hi David
Can I just confirm that you have carried out the following steps
1. You have opened your new resource pool as well as the file that you wish to link to it
In the file that is to use the new resource pool you have gone to TOOLS-RESOURCESHARING_SHARERESOURCES.
In the use resources from dialog you hjave replace the old resource pool with the new resource pool.
If you have carried out these steps, then please let me know so we can explore other options
Regards
Stephen
RE: Project 2007 - Changing Resource Pools
I think I've manage to find a solution to the above Dilema.
Open-Up new Resource Pool 10 - then
Open Individual Project file, a message window appears
'Can't find original Resource Pool Link - do you want to disconnect the link?? Click-Yes
The Project file should then open, go to Tools in top toolbar.
Share Resources - the new Resource Pool 10 Link should now appear in the drop-down options box - Click on new Link - OK
So far the above has allowed me to progress
- Thank Goodness
Regards David
RE: Project 2007 - Changing Resource Pools
Hello David
Thank you for your post.
We have had an MS Project trainer review your query, and this scenario would take quite a bit of dedicated time to resolve and therefore it is beyond our capacity to answer your question via the forum.
We would be able to offer assistance in a consultative capacity, for which there would be an associated cost.
If you would be interested in taking this forward and receiving a quote, please contact our enquiries team on phone number or email info@stl-training.co.uk
Regards
Best Training
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Inserting Task Durations QuicklyWhen entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day. |