How do i share resources between a number of projects?
RE: Sharing resources
Hi Sarah
thanks for your question. First you need to have a project file that holds the list of your resources. Ideally this file will have only resource information in it, no tasks at all. This file will become your resource pool. With your resource pool open in the background open your project file and go to Tools > share resources > resource sharing.
Select the radio button to share resources from the open resource pool file and click on OK. This will populate your project plan with resources from the resource pool that you created. You can now assign them to tasks in your project.
You can repeat this with multiple projects sharing the same resources from a single resource pool.
Hope this his helpful.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Email a TaskWhen you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system. |