Hi,

Is there a way to take a task (with numerous sub-tasks) out of project and make it into an individual project?

Purpose: After creating a project you would like to give control to one member of your team of a certain task, without giving them the full master project.

Thanks

Dougy

RE: Task -> Seperate project

The only way I know of doing this is to copy the section of the project into a new project. Then replace the selection in the original section with a linked project.

You will need to re-link and links the selection had to the rest of the project.

The does not appear to be an automatic method of splitting a project file into seperate projects.

Laura


 

MS Project tip:

Formatting Bar Text

To display notes or resource initials on the Gantt chart bars, choose Format, Bar Styles and the Text tab. Select the position you want to show the text i.e. Top or Inside etc, then choose the field name you are looking for from the drop down arrow. Type the first letter of the name to get quickly to the top of the letter range. Click OK.