View Live Stats View ReviewsForum home » Delegate support and help forum » Microsoft Project Training and help » Variance
Variance
Resolved · High Priority · Version 2003
Rajkumar has attended:
No courses
Variance
Even though i have not started any progress updation, when i switch to the variance, (from the 0 cell), the value of the variance isa showling for some tasks. what might be the reason. I havnt saved the baseline yet.
thanks
raj
RE: Variance
Hi Raj
The Variance column is automatically populated when you assign resources to rasks. When you save the baseline, it will reset the variance column to zero.
When you attend the Project course this will be covered.
Alan Burbridge
Best STL
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Giving Someone a Gantt Chart SnapshotTo pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010) |