Forum home » Delegate support and help forum » Microsoft Project Training and help » Variance

Variance

resolvedResolved · High Priority · Version 2003

Rajkumar has attended:
No courses

Variance

Even though i have not started any progress updation, when i switch to the variance, (from the 0 cell), the value of the variance isa showling for some tasks. what might be the reason. I havnt saved the baseline yet.

thanks
raj

RE: Variance

Hi Raj

The Variance column is automatically populated when you assign resources to rasks. When you save the baseline, it will reset the variance column to zero.

When you attend the Project course this will be covered.

Alan Burbridge
Best STL


 

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips


Server loaded in 0.08 secs.