where can I find how to create resourcing pool

RE: resourcing

Hi Pauline

You could attend our Project Advanced course!

A resource pool is a seperate Project which contains only Resource information. Each project then needs to be told to Share Resources from the Resource Pool - see the Tools menu for this option.

It is not as simple as this - you really should attend the course.

Good luck.

Alan Burbridge


 

MS Project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.