98.7% Of all customers recommend us, we're so confident about our results we publish all reviews and stats
View Live Stats View ReviewsForum home » Delegate support and help forum » Microsoft Project Training and help » Project 2007 - summary tasks non displaying % | MS-Project forum
Project 2007 - summary tasks non displaying % | MS-Project forum
Resolved · Medium Priority · Version 2007
Enrico has attended:
Project Intro Intermediate course
Project 2007 - summary tasks non displaying %
Hi,
I have a couple of issues with Project 2007.
1) Project is not showing the % comlplete in the summary tasks.
2) When I update the percentage complete in the table (I.e. from 0 to 50%), projects it still displays 0%.
If I split the screen and update the % complete from there it works.
Any idea?
Are you aware of any bug in Project 2007?
Thanks
Enrico
RE: Project 2007 - summary tasks non displaying %
Hi Enrico
For the summary tasks, go to FORMAT, BAR STYLES and choose SUMMARY from the left hand column.
Then click the TEXT tab below, and from the drop down button next to RIGHT, choose % COMPLETE. That should solve the problem.
As for point 2, I cannot understand this. It may be a problem with your own software. Are you using a Beta version? You could try re-installing or better still contact Microsoft themselves at www.microsoft.com
Alan Burbridge
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Typing Links Between TasksIn the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between. |