Forum home » Delegate support and help forum » Microsoft Project Training and help » Sharepoint

Sharepoint

resolvedResolved · Low Priority · Version 2003

Bethany has attended:
Project Intro Intermediate course

Sharepoint

How does Project 2003 link in with Sharepoint and calendars?
Thanks!

RE: Sharepoint

Hi Bethany,

Thank you for your question.

I do not know too much about Sharepoint but after taking some advice, you can send your Project to Sharepoint and by using a plug-in, people can pull up the Gantt chart without the need for the software.

Project Server is needed for any real network sharing of Calendars. When on eof my colleagues returns to the office, I will ask him and update you via email.

I hope this answers your question.

Regards

Simon


 

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips