cost relation project plan

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » Cost relation with project plan

Cost relation with project plan

resolvedResolved · Medium Priority · Version 2007

Averrouz has attended:
Project Intermediate course

Cost relation with project plan

How to solve the cost changes in the project plan when there's price different between the previous cost when we start the project and in the middle of the project?

RE: Cost relation with project plan

Hi Averrouz

If your cost rates change during the plan you can adjust your model as follows:

On the resource sheet (View > resource sheet) double click on a resource. In the dialogue box that appears click on the costs tab. You will see cost rate table A. Initially it will only have one row in it. The row begins with an effective date of -- meaning the rate applies from the beginning of the project.
In the next row down enter the date the cost for this resource changes. In the next cell enter the new standard rate or enter the % change and Project will calculate the new rate.
Repeat this for each affected resource and Project will apply the new rate after the date you specify.

Hope this helps. Let us know if you have any further questions.

Kind regards,

Andrew


 

MS Project tip:

Project Community

in the help menu type "Tips" then select "Ask the Project community" this takes you into microsofts site where you can ask questions to lots of knowledgeable people.They make up an online group of experienced Project users who answer questions and provide solutions and tips.

View all MS Project hints and tips