Calander
Resolved · Low Priority · Version 2007
David has attended:
Project Intermediate course
Calander
How do I format the calander to class all days as work days (7 days a week)
RE: Calander
Hi David
You can do this quickly by going to Tools > Change Working Time. At the bottom of the calendar click on the Work Weeks tab. Choose the row entry called Default and click on details. Use this control to set the weekends to work days, keying in the specific hours for those days in line with the rest of the week and click OK. Before you leave change working time you might also want to click on Options and at the bottom of the screen change the hours per week from 40 (5 days) to 56 (7 days)
I hope this helps - let us know if you have any further questions.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Email a TaskWhen you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system. |