recurring tasks

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » Recurring Tasks

Recurring Tasks

resolvedResolved · Urgent Priority · Version 2007

Samir has attended:
Project Intro Intermediate course

Recurring Tasks

Hi there
Can you please let me know how you
assign recurring tasks in projects for example :
if i want to show weekly or monthly progress meetings as milestones on my programme
Regards
Thank you kindly.
s khan

RE: Recurring Tasks

Hi Samir

Thank you for your question

If you click on the Insert menu and select recurring tasks.

You can then use the wizard and specify

The task Name
The duration (set zero for milestones)
The recurrance pattern
The start and end dates for the first and last occurence, (if required)

Hope this is useful

If you require further advice, please get back to me

Regards

Stephen


 

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips


Server loaded in 0.1 secs.