Hi there
Can you please let me know how you
assign recurring tasks in projects for example :
if i want to show weekly or monthly progress meetings as milestones on my programme
Regards
Thank you kindly.
s khan
RE: Recurring Tasks
Hi Samir
Thank you for your question
If you click on the Insert menu and select recurring tasks.
You can then use the wizard and specify
The task Name
The duration (set zero for milestones)
The recurrance pattern
The start and end dates for the first and last occurence, (if required)
Hope this is useful
If you require further advice, please get back to me
Regards
Stephen
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Inserting Task Durations QuicklyWhen entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day. |