Project

How do you link resources accross multiple projects to check for conflicts?

RE: Project

Hi Bill

This is created using a resource pool which is a central project file containing a list of your resources. To share these resources with a project file open both the resource pool then switch to the project and from tools > resource sharing > share resources connect to the pool. You can now assign central resources as if they were part of the project file.
The resource pool keeps track of availability and over allocation.

Hope this is helpful - let us know if you have any further questions.

Kind regards,

Andrew


 

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips