Forum home » Delegate support and help forum » Microsoft Project Training and help » Linking calenders

Linking calenders

resolvedResolved · Low Priority · Version 2003

Pauline has attended:
Project Intro Intermediate course

Linking calenders

How do you link calenders running simultaneously?

RE: linking calenders

Hi Pauline

Individual calendars remain independent of each other.
The closest example of one calendar driving another is on the resource sheet where you set the calendar that will be the base for each resource (by default this is set to standard).

Hope this helps. Do let us know if you have any other questions.

Kind regards,

Andrew


 

MS Project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.