Baseline

resolvedResolved · High Priority · Version 2003

Pauline has attended:
Project Intro Intermediate course

Baseline

Is it possible to get a wider more detailed understanding of baseline?

RE: Baseline

Hi Pauline

You can save the baseline by going to Tools > Tracking > Save Baseline.

MS Project then copies the start, finish, duration, work and cost information for each task. You would do this when the project is ready to start but before any progress has been recorded.

Now when you update your project you can compare your live plan with the baseline by going to the Tracking Gantt chart (View > Tracking Gantt). The coloured bars represent your live project, the grey lines represent the baseline.

I hope this is helpful - do let us know if you have any further questions.

Kind regards,

Andrew


 

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips


Server loaded in 0.1 secs.