where do i find to change the critcical path
RE: ms project
Hi Pauline
thanks for your question. You can view the Critical Path by going to View > Tracking Gantt. Although the Critical Path is calculated for you by MS Project you can adjust how it determines if a task is critical or not. Go to Tools > Options > Calculation and change the last option in the dialogue box "Tasks are critical if slack is less than or equal to __ days"
I hope this is helpful - let us know if you have any further questions.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Entering DaysTo type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date. |