If planning events i.e Meeting offsite, in regards to resources can i allocate a meeting room/accommodation as a resource?
RE: Resources
Hi Sarah
Thanks for your question. You can set a room or piece of equipment as a resource. In this instance you would be best setting the resource type to "work" and setting Max Units to reflect how much resource you have available. This in turn would enable you to spot any over allocation in your project.
I hope this helps - do let us know if you have any other questions.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Create own ribbon tab - Project 2010a. In Project click on the File tab |