please confirm /advise in respect of the creation of float and slack and milestones/constraints
RE: microsoft project
Hi Mark
Float is created where two tasks are linked (e.g. finish to start) and the successor is constrained beyond the finish of its predecessor. A partial constraint type is Start no earlier than SNET (reached via double clicking on the successor name then choosing the advanced tab). The successor could be a task or a milestone (0 duration).
I hope this helps. Do let us know if you have any further questions - kind regards, Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Typing Links Between TasksIn the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between. |