how do I see the none workign days again after viewing in entire project view?

RE: view

Hi Sarah

Thanks for your question. As you've found if you use View > zoom > entire project the Gantt chart is resized to accommodate your plan but this often means days are dropped from the time line and non-working days are not shown. A single click on the zoom-in icon should drop you back to a days of the week view that shows non-working time such as weekends.

Hope this helps - let us know if you have any other questions.

Kind regards,

Andrew


 

MS Project tip:

Set default task type - Project 2010

a. In Project, click on the File tab
b. Select Options from left hand side
c. Click on Schedule to set the scheduling options
d. Set the Default Task type box to your chosen option
i. Generally if you plan/estimate your projects using durations you should use fixed duration, and untick the box New tasks are effort driven, if you plan/estimate with person hours use fixed work, or for plans estimated with the proportion of resources time use fixed units, and untick the box New tasks are effort driven)
e. Click OK to apply your changes