project courses london - Baseline

resolvedResolved · Low Priority · Version Standard

John has attended:
Project Intro Intermediate course
Project Advanced course
Visio Introduction course

Baseline

How to retrieve individual/specific Baselines?

RE: Baseline

On the Tools menu, point to Tracking, and then click Save Baseline.

Save baseline section

Save Baseline When you click Save baseline, you can specify the baseline you want to save. You can save up to 11 different baselines. Baseline information is stored in the Baseline Start, Baseline Finish, Baseline Work, Baseline Duration, and Baseline Cost fields.

Baseline fields

Baseline Click to save the current project to this baseline.

Baseline1-10 Click any of these custom baseline fields to save the current project to the selected baseline.

Notes


The start and finish dates for tasks are updated as you adjust and track your project. By creating a baseline plan, you can compare the most current information (stored in the start and finish fields), with the baseline information (stored in the baseline fields).

To view a baseline plan after you have saved it, display the Tracking Gantt view with the Tracking or Variance table applied.
To view more than one baseline plan, goto view then more views and select the Multiple Baselines Gantt view.


 

MS Project tip:

Giving Someone a Gantt Chart Snapshot

To pass on a picture of a Gantt chart segment, choose the appropriate view, select the rows to be included, then click on the camera icon and select For Screen. The graphics image can be pasted into another document. (See Paste icon forn Project 2010)

View all MS Project hints and tips