How can I create hammock links?

RE: Project

To build a hammock task between two other tasks, follow these steps:

Click in a row in the Gantt chart where you want to create the hammock task.

Click Insert Task on the Insert menu.

In the Task Name cell of the Gantt chart, type the name for the task.

Click the cell in the Gantt chart that contains the date that controls the start of the hammock task. This date can be the Start date or the Finish date of a task. In the figure, this date is the Start date for the Move And Cover Furniture task.

On the Edit menu, click Copy Cell.

Click the Start date cell for the hammock task.

On the Edit menu, click Paste Special.

In the Paste Special dialog box, click the Paste Link option, and then click OK to link the start date of the hammock task to the start date of the controlling task.


 

MS Project tip:

Using the Quick Access Toolbar in Project 2010

The Quick Access Toolbar is included in virtually every Office product, including Project 2010 as well as Outlook 2010, Word 2010, Excel 2010, and PowerPoint 2010.

You will find the Quick Access Toolbar in the top-left side of the window. To begin, click the Customize button (it's the little black arrow at the end of the toolbar).

Simply click the commands you want to include.

Virtually any command can be added to the Quick Access Toolbar. Click the More Commands option and a new window will open from where you can browse the commands including those not on the ribbon.

View all MS Project hints and tips


Server loaded in 0.08 secs.