Baseline dates - Use and function
Resolved · Urgent Priority · Version 2003
Sudeep has attended:
Project Intro Intermediate course
Baseline dates - Use and function
(Post removed at the request of the poster)
RE: Baseline dates - Use and function
Hi Sudeep
the baseline is saved by going to Tools > Tracking > Save Baseline. Project copies the start, finish, duration, work and cost information for each of tasks into corresponding baseline fields. This is usually done once the project is ready to start but before any progress has been recorded. As your project progresses you can compare the original baseline plan with your current plan to spot variances.
The quickest way to see the baseline alongside your live plan is to switch to the Tracking Gantt chart (View > Tracking Gantt). The coloured bars represent your live project, the charcoal grey lines represent the baseline.
Alternatively in the regular Gantt Chart view (View > Gantt chart) you can get project to draw the baseline alongside your tasks. From the Format menu choose Gant Chart Wizard, click Next and choose baseline. Click Finish, Format it then exit. To remove the baseline from the Gantt chart re-run the wizard choosing standard as the formatting option.
Hope this helps - let us know if you need any further information.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Avoid Accidental ConstraintsThe initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.) |