microsoft project

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » Microsoft Project

Microsoft Project

resolvedResolved · Low Priority · Version 2007

Pete has attended:
Project Introduction course
Project Intermediate course
Visio Advanced course

Microsoft Project

Hi, How do I shift a whole projects start date by 3 months????

RE: Microsoft Project

Hi Pete

You can move a project, even if it has contstraints in it, by going to View > Toolbars > Analysis and on the Analysis toolbar clicking the adjust dates button and entering the new start date.

Hope this helps - let us know if you have any other questions.

Kind regards,

Andrew


 

MS Project tip:

Autofit column width – Project (all versions)

At the top of the columns where each column name is located (Task Name, Duration, etc.), hover over the vertical column line which you want to move.

A short bold vertical line will appear, with horizontal arrows pointing left and right.

Left click and hold this icon and it will permit you to grab the column line, allowing you to move it left or right to your desired location.

View all MS Project hints and tips


Server loaded in 0.09 secs.