Can you allocate costings to be per thousand? Eg. if working with large projects where nothing is less than

RE: Costings

Hi Sarah

Thanks for your question. For a material resource set the material label (unit) to something that indicates you are working in units of 1000 (eg 1K) and in the cost cell set the appropriate rate. Now when you assign one of this resource you are in fact assigning 1000 and project is calculating the cost accordingly. Hope this helps. Let us know if you have any other questions.

Kind regards,

Andrew


 

MS Project tip:

Create own ribbon tab - Project 2010

a. In Project click on the File tab
b. Select Options from left hand side
c. Choose the Customize Ribbon section
d. Click the New Tab button (below the list of tabs on the right hand side of the dialog box)
e. Select the New Tab (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
f. Select the New Group (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
g. Add commands to your tab and group by locating them on the list on the right hand side (remembering that you can change the list using the drop down box at the top of the list of commands) and clicking the Add button between the two panes to add them to your tab and group
h. You can rearrange the commands in your group, the groups on any tab or the tabs, using the up and down arrow buttons beside the list of tabs.
i. Click OK to apply your changes