Hi,
when I copy and paste a task in Gantt Chart view, the colour of the bar doesn't copy over - it defaults to blue.
Is there any way I can copy the formatting over?
Many Thanks in Advance
Martin
RE: Copying Task in Gantt Chart
Hi Martin
I've checked and unfortunately Project will only copy/paste the formatting of the bars in the same project. If you copy and then paste to a new project the formatting reverts back to the default (generally blue) colour.
Thanks
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Create own ribbon tab - Project 2010a. In Project click on the File tab |