What is the easiest way to print only the tasks?

RE: MS project

Hi Martyn

You can achieve this by going to View > more views... and choosing Task Sheet from the list. This is a view of the Project without the Gantt area. When you have finished you can go back to the normal Gantt view by repeating the process i.e. View > Gantt Chart

Hope this helps - let me know if you have any questions.

Kind regards,

Andrew


 

MS Project tip:

Using the Quick Access Toolbar in Project 2010

The Quick Access Toolbar is included in virtually every Office product, including Project 2010 as well as Outlook 2010, Word 2010, Excel 2010, and PowerPoint 2010.

You will find the Quick Access Toolbar in the top-left side of the window. To begin, click the Customize button (it's the little black arrow at the end of the toolbar).

Simply click the commands you want to include.

Virtually any command can be added to the Quick Access Toolbar. Click the More Commands option and a new window will open from where you can browse the commands including those not on the ribbon.