Calender

How to change the times from default to 9am - 5.30pm?

RE: Calender

Hi Julie

thanks for your question.

This process takes a couple of steps.

First, go to tools-change working time and (assuming standard is the default calendar for your project) select the column headings for Monday to Friday and set the start time from 08:00 to 09:00 and the end time to 17:30

Next, click on the options button.
Adjust the start time to 09:00 and Finish time to 17:30 (matching the calendar changes you just made) then set the hours per day to 7.5 and hours per week to 37.5

Lastly you can make sure that your Project starts at the correct time too.

Go to Tools>Options>View and select a date format that includes the time.

Got to your Project start (Project menu then Project Information) and see if your Project is starting at 9:00 or the old time of 8:00. Correct if necessary.

Also if you have tasks already in the plan you might want to check their start and finish times are correct too. If you have reduced the amount of work in a day you may find your durations need correcting.

Hope this helps - best to make a backup of your plan before trying this to make sure you are happy with the results before proceeding with the rest of your plan.

Do let us know if you have any further questions. Kind regards, Andrew


 

MS Project tip:

Create own ribbon tab - Project 2010

a. In Project click on the File tab
b. Select Options from left hand side
c. Choose the Customize Ribbon section
d. Click the New Tab button (below the list of tabs on the right hand side of the dialog box)
e. Select the New Tab (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
f. Select the New Group (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
g. Add commands to your tab and group by locating them on the list on the right hand side (remembering that you can change the list using the drop down box at the top of the list of commands) and clicking the Add button between the two panes to add them to your tab and group
h. You can rearrange the commands in your group, the groups on any tab or the tabs, using the up and down arrow buttons beside the list of tabs.
i. Click OK to apply your changes

View all MS Project hints and tips