Can I enter a percentage value against resource's task proficency?
RE: Entering Resources
Hi Jason
Thank you for your question
The simplest approach is to create a custom number field.
1. Click on Tools-Customise-Fields
2. In the field type dialog select Number
3. Select Number1 on the list and click rename
4. Rename the column something like "Task Proficiency %"
5. Click OK
You have now created your custom field. You now need to insert it into the resource sheet.
1. Open your resource sheet
2. Right click on a column head where you want your new column to go
3. Select Insert from the context menu
4. In the field dialog select "Task Proficiency % (Number 1)"
You can now enter proficiency ratings for each resource. It seems likely that you will want proficiency ratings for different types of task. There are 20 number fields, so you can repeat the process using number 2 through to number 20 for your different task types
Hope this is useful. If you have any further queries please do not hesitate to get back to me
Regards
Stephen
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Entering DaysTo type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date. |