Resources
Resolved · Low Priority · Version 2003
Ian has attended:
Project Intro Intermediate course
Project Intermediate course
Resources
I need to add more resources doing different related task working towards a common goal
RE: resources
Hi Ian
Thanks for your question. You can add more resources to a task by splitting the screen (window > split), choosing the task in question then in the lower left corner of the screen choosing your resources. Be careful though about adjusting tasks that already have resources. Project may adjust your task's duration. Check whether effort driven scheduling is enabled as well as the current task type - the controls are in the centre of the screen just below the split bar.
If you have any further questions please don't hesitate to let us know.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Set default task type - Project 2010a. In Project, click on the File tab |