Calendars
I have my calendar set to the standard base setting, I type in "1 day" but when I look back at it, it keeps saying "0.94 days" instead.
Please can you let me know what I can do to recitify this.
Thanks.
RE: Calendars
Hi Calire
Thank you for your question
This is most likely caused by one of the following:
1. The calendar settings found in Tools-Options- Calendar do not match the settings specified in your standard base calendar. Make sure that the day start and end times, together with hours per day and hours per week match
2. If you have resources allocated to the task and one of the resources' calendars differes from the standard calendar then this too will change the duration of the task as the individual resource calendar overides the standard project calendar.
3. You specified a duration for the task, and then changed the base calendar. This too could cause discrepencies in duration.
Hope one of the above proves helpful, if not please let me know so I can explore other avenues
Regards
Stephen
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Using the Quick Access Toolbar in Project 2010The Quick Access Toolbar is included in virtually every Office product, including Project 2010 as well as Outlook 2010, Word 2010, Excel 2010, and PowerPoint 2010. |