Forum home » Delegate support and help forum » Microsoft Project Training and help » Deadlines

Deadlines

resolvedResolved · Low Priority · Version 2007

anthony has attended:
Project Introduction course

Deadlines

Why don't deadlines show up in the calendar view?

RE: Deadlines

The bars are generally too short! To display deadlines:

1. Right click a task box and choose Bar Styles.
2. In the Task Type box, choose Noncritical
3. In the Fields box, type a comma after the last field
4. Click the dropdown arrow and choose Deadline
5. Repeat steps 1 to 4 but in step 2 choose Critical

Hows that?


 

MS Project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.