microsoft project training london - Multiple projects

resolvedResolved · Low Priority · Version Standard

Rebecca has attended:
Project Intro Intermediate course

Multiple projects

How do I link multiple projects?

RE: multiple projects

1. Open up the project files you want to link
2. go to window on the menu bar and select New Window
3. select the project files you want to link in the New Window dialog box and click OK.
Now they are all linked into a master project file


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips