ms project

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » MS Project

MS Project

resolvedResolved · Low Priority · Version 2003

Jo has attended:
Project Intro Intermediate course

MS Project

If I need to set up a new project with a non optional deadline of getting a water station into operation so it can serve the local area, would that be classed as the sucessor and would it be a finish to start project(ie back to front)?

RE: MS Project

Hi Jo

Thanks for your question - good example too. The thing that would help you decide is the question: "Which of the two tasks is driving or positioning the other? Once you've chosen the predecessor (or driving task) you can then decide if it's the start or finish that's doing the driving. Finally you can assess if it's affecting the start or finish of the successor. With all that in place you may indeed end up with a task in the future being the predecessor to an earlier task with a Start Finish relationship.

Hope this helps, do let us know if you have any other questions. Kind regards,

Andrew


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Server loaded in 0.09 secs.