Re-occuring activities

How do you create multiple re-occurring activities?

RE: Re-occuring activities

Hi Paul

to set up recurring activities got the menu bar and choose Insert > Recurring task From here you can create a task, specify its duration and recurrance pattern and Project will do the hard work of creating all the activities for you.

Hope this helps - let us know if we can be of further assistance.

Kind regards,

Andrew


 

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)