Will insterting a new task automatically insert the predecessor?
RE: Predecessors
Hi Charlene
Thanks for your question - yes it can. You can control this option by going to the schedule tab (tools > Options > schedule) and de-selecting "autolink insterted or moved tasks"
Hope this helps - let me know if we can be of further assistance.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Link tasks using predecessor column - projecta. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number. |