Predecessors

Will insterting a new task automatically insert the predecessor?

RE: Predecessors

Hi Charlene

Thanks for your question - yes it can. You can control this option by going to the schedule tab (tools > Options > schedule) and de-selecting "autolink insterted or moved tasks"

Hope this helps - let me know if we can be of further assistance.

Kind regards,

Andrew


 

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.