Can you specify a resource as a room, which can only be used by one task at a time?
RE: Resources
Hi Emily
Yes you can. In Project 2003 there are two type of resource - Work and material. Setting a room resource as Work will enable you to spot if it's been overallocated in your schedule.
Hope this helps - let us know if you have any further questions.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Formatting Bar TextTo display notes or resource initials on the Gantt chart bars, choose Format, Bar Styles and the Text tab. Select the position you want to show the text i.e. Top or Inside etc, then choose the field name you are looking for from the drop down arrow. Type the first letter of the name to get quickly to the top of the letter range. Click OK. |