Can you specify a resource as a room, which can only be used by one task at a time?

RE: Resources

Hi Emily

Yes you can. In Project 2003 there are two type of resource - Work and material. Setting a room resource as Work will enable you to spot if it's been overallocated in your schedule.

Hope this helps - let us know if you have any further questions.

Kind regards,

Andrew


 

MS Project tip:

Formatting Bar Text

To display notes or resource initials on the Gantt chart bars, choose Format, Bar Styles and the Text tab. Select the position you want to show the text i.e. Top or Inside etc, then choose the field name you are looking for from the drop down arrow. Type the first letter of the name to get quickly to the top of the letter range. Click OK.