Resolved · Low Priority · Version 2007
RE: working time
Hi Sharon
thanks for your question - you can do this by going to Tools > Change working time. The calendar allows you to modify the base Standard calendar for your project.
Hope this helps - let us know if you have any other questions.
Kind regards,
Andrew
Training information:
See also:
Welcome. Please choose your application (eg. Excel) and then post your question. Our Microsoft Qualified trainers will then respond within 24 hours (working days). Frequently Asked Questions
Any suggestions, questions or comments? Please post in the Improve the forum thread. |
MS Project tip:Format individual bars on your GANTT chartTo draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications. |