getting rid weekend days

Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

Forum home » Delegate support and help forum » Microsoft Project Training and help » Getting rid of weekend days on Gantt

Getting rid of weekend days on Gantt

resolvedResolved · Medium Priority · Version 2003

Kathryn has attended:
Project Intro Intermediate course

Getting rid of weekend days on Gantt

I don't want to see Saturdays and Sundays in my Gantt chart. I have amended the working time so that Sat and Sun is non working time and I have changed the formating so non working time should not be shown but it is still showing on the Gantt chart. What am I doing wrong?
Thanks,
Kathryn

RE: Getting rid of weekend days on Gantt

All you can do is use the magnifyinh glasses to change the view to one which does not show Saturdays and Sundays. It is not possible to remove them from the default Gantt view.


 

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips


Server loaded in 0.08 secs.